Day 1 (3/3): Brainstormed mission goals, found Callisto as our eventual destination. Began drafting mission statement.

Day 2 (3/5): Worked on mission statement, found information on Callisto. Began drafting designs of our rover.

Day 3 (3/6): Finalized mission statement, tools, and planetary information.

Day 4 (3/12): Made Logos, slogan.

Day 5 (3/15): Worked on design, finalized logo, and began to create the kindergarden project.

Day 6 (3/19): Finalized the design, posted logo & slogan, and finished the kindergarden project.